Options Page of the Advance Calendar Wizard
Use this page to select the options for advancing the calendar assigned to a project.
Contents
Field | Description |
---|---|
Automatically change the status of LOE Work Package to in-progress | The default option for this checkbox depends on whether the corresponding option is selected on the Preferences tab of the Project Properties dialog box.
If this option is marked as Secure on the Preferences tab of the Project Properties dialog box, Cobra disables this checkbox for users who do not have access rights to the preferences for this project. If this option is not selected, Cobra ignores the status date and the actual start date for the work package will not change. |
Skip rolling wave processing | Select this option to advance the calendar without running the rolling wave process. By default, this option is cleared.
This option is disabled if there is no rolling wave calendar assigned to the project. |
Expanded Data Window | Cobra disables the
Expanded Data Window group box on this page if:
Rolling Wave Calendar The following options are available when a rolling wave calendar is assigned to the project:
|